LESCO New Connection 2025

The government has introduced a centralized web portal for LESCO new connections. Now you can apply for a new connection, name change, load change, or tariff change online through the ENC official website.
How To Apply For LESCO New Connection
Documents Required
Printing and Submission
WAPDA focal persons may verify your address and documents in person.
Demand Notice (DN)
Tracking Your Application For LESCO New Connection
Steps:
Installation of Meter
After verification of the paid demand notice, your new connection is approved and a meter is installed at the specified address.
Time Required for LESCO New Connection
Category 1 (Load up to 15kW)
| Process Step | Time |
| Total time | 30 days |
| Application receipt & seniority | 1 Day |
| Site inspection | 3 Days |
| Cost estimation | 2 Days |
| Delivery of DN | 2 Days |
| Submission of DN receipt | 2 Days |
| Wiring test report submission | 3 Days |
| Priority list preparation | 1 Day |
| Issue of connection order | 3 Days |
| Store request for material | 3 Days |
| Material delivery | 5 Days |
| Installation of connection | 5 Days |
Category 2 (Load 16–70kW)
| Process Step | Time |
| Total time | 30 days |
| Application receipt & seniority | 1 Day |
| Site inspection | 4 Days |
| Cost estimation | 3 Days |
| Delivery of DN | 4 Days |
| Submission of DN receipt | 2 Days |
| Wiring test report submission | 5 Days |
| Priority list preparation | 2 Day |
| Issue of connection order | 4 Days |
| Store request for material | 15 Days |
| Material delivery | 7 Days |
| Installation of connection | 6 Days |
Category 3 (Load 71–500kW)
| Process Step | Time |
| Total time | 73 days |
| Application receipt & seniority | 1 Day |
| Site inspection | 4 Days |
| Cost estimation | 2 Days |
| Acceptance by office | 4 Days |
| Submission of DN receipt | 4 Days |
| Wiring test report submission | 4 Days |
| Issue of LESCO new connection order | 2 Day |
| Store request for material | 15 Days |
| Installation by committee | 37 Days |
Change of Name / Load / Tariff
Steps:
Attach documents (max 300kb):
Submit and Print
Print & Pay DN
Check your LESCO online bill here.
Conclusion
You can apply online for a new connection or changes to an existing one. Just follow the steps. You can track your application via the tracking ID.