LESCO New Connection 2025

LESCO NEW CONNECTION

The government has introduced a centralized web portal for LESCO new connections. Now you can apply for a new connection, name change, load change, or tariff change online through the ENC official website.

How To Apply For LESCO New Connection

  • Click “Apply” from the left-side menu.
  •  Fill out the tabs: Company (LESCO), Subdivision, Category, Reference Number.
  •  Enter the reference number of your neighbor.
  •  A detailed form will appear. Fill in your details: name, father’s name, ownership, CNIC, mobile number, citizenship, and address.
  •  Provide premises details: existing meters, load required, installation address.
  • If not satisfied with services, register a complaint online via the Complaint Management System.

Documents Required

  • Upload scanned copies (less than 300kb each):
  • Property documents: Fard, Registry, or property file.
  • Attested CNIC (applicant and witness).
  • Neighbour’s electricity bill. Wiring contractor’s test report.
  • Applicant undertaking.
  • Submit your online application. A tracking ID will be provided.

Printing and Submission

WAPDA focal persons may verify your address and documents in person.

Demand Notice (DN)

  • Visit [http://www.enc.com.pk]
  • Click “Print DN” and enter your tracking ID.
  • Pay the DN at a designated branch or online.
  • Upload the paid DN copy to the portal and submit it to the office.

Tracking Your Application For LESCO New Connection

Steps:

  • Visit [www.enc.com.pk](http://www.enc.com.pk)
  • Click “Track” from the left sidebar.
  • Select application type (new connection).
  • Choose company (LESCO).
  • Enter your tracking ID.

Installation of Meter

After verification of the paid demand notice, your new connection is approved and a meter is installed at the specified address.

Time Required for LESCO New Connection

Category 1 (Load up to 15kW)

Process StepTime
Total time30 days
Application receipt & seniority 1 Day
Site inspection3 Days
Cost estimation2 Days
Delivery of DN2 Days
Submission of DN receipt 2 Days
Wiring test report submission3 Days
Priority list preparation1 Day
Issue of connection order3 Days
Store request for material3 Days
Material delivery5 Days
Installation of connection5 Days

Category 2 (Load 16–70kW)

Process Step Time
Total time 30 days
Application receipt & seniority 1 Day
Site inspection4 Days
Cost estimation3 Days
Delivery of DN4 Days
Submission of DN receipt 2 Days
Wiring test report submission5 Days
Priority list preparation2 Day
Issue of connection order4 Days
Store request for material15 Days
Material delivery7 Days
Installation of connection6 Days

Category 3 (Load 71–500kW)

Process Step Time
Total time 73 days
Application receipt & seniority 1 Day
Site inspection4 Days
Cost estimation2 Days
Acceptance by office4 Days
Submission of DN receipt 4 Days
Wiring test report submission4 Days
Issue of LESCO new connection order2 Day
Store request for material15 Days
Installation by committee37 Days

Change of Name / Load / Tariff

Steps:

  • Visit [http://www.enc.com.pk/](http://www.enc.com.pk/)
  • Click “Change” from the left menu.
  • Select application type: name, load, or tariff change.
  • Fill in details: reference number, CNIC, mobile number, name.

Attach documents (max 300kb):

  • CNIC copy
  • Recent bill
  • Proof of ownership

Submit and Print

  • Submit form and note tracking ID.
  • Click “Print” to print the application using tracking ID.
  • Attach documents and submit to the office.

Print & Pay DN

  • Visit ENC site > “Print DN” > Enter tracking ID > Print.
  • Pay fee at bank or online.
  • Upload paid DN and send to office.

Check your LESCO online bill here.

Conclusion

You can apply online for a new connection or changes to an existing one. Just follow the steps. You can track your application via the tracking ID.